A home chargepoint is fixed electrical work. In the UK the Energy Saving Trust says you need a registered chargepoint installer; in the US the Department of Energy recommends a certified electrical contractor. This is not a DIY job.
Do you need one?
The Energy Saving Trust says you do not have to install a home chargepoint, but that charging at home is the cheapest way if you have a driveway or garage. Without off-street parking you can use public on-street chargepoints, or shared home chargepoints through services such as Co Charger or Zapmap.
Steps in the UK
The Energy Saving Trust lists three steps:
1. Find and buy a chargepoint.
2. Find a registered chargepoint installer. The Electric Vehicle Consumer Code for Home Chargepoints has resources on choosing one.
3. Register the chargepoint with your Distribution Network Operator. It says your installer usually does this for you.
It also points to the UK Government’s electric vehicle chargepoint grant, which it says offers up to £350 per socket for residential landlords, people living in flats and people who rent.
Steps in the US
The US Department of Energy’s Alternative Fuels Data Center says most drivers charge overnight with Level 1 or Level 2 equipment, recommends safety-certified equipment such as ENERGY STAR products and a certified electrical contractor, and says an electrician can tell you whether your home has enough electrical capacity. It says installations must follow local and state codes, permits may be needed, and NEC Article 625 covers most of the rules for charging equipment.
How long it takes
The Energy Saving Trust says a rough rule is that a charger’s power in kW is about the number of miles you add in 20 minutes: a 7 kW charger gives roughly 7 miles of range for every 20 minutes. Its table says a 7.4 kW home charger takes about 7 hours 45 minutes to charge a 50 kWh battery from 20%.